Hardwood and laminate flooring calculator

14′ × 12′ floor: 168 sq ft is 10 boxes (20 sq ft each), with a ¾″ gap at the walls and the underlayment and fasteners counted. Install solid or engineered hardwood or laminate, or sand and refinish an old wood floor.

Free, no account needed. Type your own sizes and every line is counted again.

Worked example · feet and inches (New Jersey) or metric (Ontario)

Sheet S-11 · Hardwood and laminate floors

14′ × 12′ floor

DIY OK
PLANboards along the length, end joints staggered14′12′AT THE WALLsection, 3× scale¾″123456789
Plan + wall detail
Boxes
1020 sq ft each
Floor
168sq ft
Gap
¾″at the walls
Method
Nailedsolid

Tools you need

  • Tape measure (25 ft)
  • Carpenter's pencil
  • Chalk line
  • Moisture meter
  • Straightedge (6 ft)
  • Miter saw

25 tools on the Sheet, each marked own, buy or rent

What to buy 8 lines, each with its math
BuyItemHow we got this
10 boxesSolid hardwood flooring ¾″20 sq ft per box, 3¼″ boards, prefinished168 sq ft + 10% for cuts (straight layout) = 185 sq ft ÷ 20 sq ft per box. Buy it all from one lot so the color matches.
1 rollAsphalt felt #1536″ × 144′ roll (432 sq ft)168 sq ft with 4″ overlaps + 5% = 198 sq ft ÷ 432 sq ft per roll. The NWFA wants a vapor retarder under nailed floors over wood: asphalt felt (ASTM D4869), not plastic.
2 boxes of 1,000Flooring cleats or staples2″ cleats or staples620 ft of 3¼″ boards, one fastener every 6″ (NWFA: 6–8″ for boards 3″ and wider), 1–3″ from each end, + 5% = ≈1,303.
1 boxFinish nails (15 or 16-ga)2″, 15-gaFace-nail the first and last rows, where the nailer can’t reach. Pre-drill hardwood so it doesn’t split.
7 piecesQuarter-round moldingshoe or quarter-round, 8 ft lengths49 ft around the room (minus doorways) + 10% for miters. It covers the ¾″ gap.
1 box18-ga brad nails1¼″Into the wall or the baseboard — never down into the floor.
1 tubePainter’s acrylic caulk (paintable)Top edge of the trim and the miters.
1 pieceT-molding or reducerT-molding, matchingOne per doorway: a T-molding to the floor at the same height.
Flooring & tile · Sheet S-11 · 01What to buy (14′ × 12′ floor)

What to buy (14′ × 12′ floor)

Every line shows the quantity to buy and how StudSheet got it: the spacing, the waste and the package size, so you can check it before the supply house or the quote.

BuyMaterialHow StudSheet counts itWhat it is for
10 boxesSolid hardwood flooring ¾″ (20 sq ft per box, 3¼″ boards, prefinished)168 sq ft + 10% for cuts (straight layout) = 185 sq ft ÷ 20 sq ft per box. Buy it all from one lot so the color matches.Solid boards, nailed down over plywood or OSB. Sold by the box, prefinished or unfinished.
1 rollAsphalt felt #15 (36″ × 144′ roll (432 sq ft))168 sq ft with 4″ overlaps + 5% = 198 sq ft ÷ 432 sq ft per roll. The NWFA wants a vapor retarder under nailed floors over wood: asphalt felt (ASTM D4869), not plastic.The vapor retarder under nailed wood floors over plywood or OSB (ASTM D4869). Not plastic: wood needs a retarder that breathes a little.
2 boxes of 1,000Flooring cleats or staples (2″ cleats or staples)620 ft of 3¼″ boards, one fastener every 6″ (NWFA: 6–8″ for boards 3″ and wider), 1–3″ from each end, + 5% = ≈1,303.Fasteners for the flooring nailer, sized to the boards: 2″ for ¾″ solid, 1½″ for thinner engineered. Boxes of 1,000.
1 boxFinish nails (15 or 16-ga) (2″, 15-ga)Face-nail the first and last rows, where the nailer can’t reach. Pre-drill hardwood so it doesn’t split.Face-nail the first and last rows where the flooring nailer can’t reach. Pre-drill hardwood.
7 piecesQuarter-round molding (shoe or quarter-round, 8 ft lengths)49 ft around the room (minus doorways) + 10% for miters. It covers the ¾″ gap.Covers the expansion gap. Nail it to the baseboard, not the floor.
1 box18-ga brad nails (1¼″)Into the wall or the baseboard — never down into the floor.For quarter-round and baseboard.
1 tubePainter’s acrylic caulk (paintable)Top edge of the trim and the miters.Fills gaps between trim and wall.
1 pieceT-molding or reducer (T-molding, matching)One per doorway: a T-molding to the floor at the same height.Bridges to another hard floor at a doorway.

In Canada (4.27 m × 3.66 m floor)

Set to Canada, the Sheet works the job out again for Ontario: metric sizes, bag sizes, the frost depth and the code notes. It doesn't just convert feet to meters. The first lines:

  • 10 boxes, Solid hardwood flooring 19 mm: 15.6 m² + 10% for cuts (straight layout) = 17.2 m² ÷ 1.86 m² per box. Buy it all from one lot so the color matches.
  • 1 roll, Asphalt felt #15: 15.6 m² with 102 mm overlaps + 5% = 18.4 m² ÷ 40.1 m² per roll. The NWFA wants a vapor retarder under nailed floors over wood: asphalt felt (ASTM D4869), not plastic.
  • 2 boxes of 1,000, Flooring cleats or staples: 189.07 m of 83 mm boards, one fastener every 152 mm (NWFA: 152–203 mm for boards 76 mm and wider), 25–76 mm from each end, + 5% = ≈1,303.
  • 1 box, Finish nails (15 or 16-ga): Face-nail the first and last rows, where the nailer can’t reach. Pre-drill hardwood so it doesn’t split.
  • 7 pieces, Quarter-round molding: 14.94 m around the room (minus doorways) + 10% for miters. It covers the 19 mm gap.
  • 1 box, 18-ga brad nails: Into the wall or the baseboard — never down into the floor.
Flooring & tile · Sheet S-11 · 02The steps, in order

The steps, in order

  1. Job site ready: heat or air conditioning running at living conditions (60–80 °F, 30–50% humidity) for at least 5 days, and drywall, paint and other wet work done and dry (NWFA).
  2. Let the wood adjust to the room: open the boxes and spread the boards out, then read the boards and the subfloor with a moisture meter each day until the readings stop changing.
  3. Prep: pull the baseboards (or just the shoe molding), undercut the door casings and jambs, and scrape, sweep and vacuum the subfloor.
  4. Check the subfloor: screw down squeaks and loose spots, flat within ¼″ in 10 ft, and plywood or OSB at 12% moisture or less, within 2% of the boards (NWFA).
  5. Roll out #15 felt across the floor, seams overlapped 4″, stapled flat.
  6. Snap a starting line ¾″ off the straightest long wall, across the floor joists, and check it for square.
  7. First rows: face-nail along the line (pre-drill), then blind-nail through the tongue until there’s room for the flooring nailer.
  8. Lay the field from several boxes at once: end joints at least 8″ apart, no H pattern; cleats every 6–8″, 1–3″ from each end.
  9. Last rows: rip the final board to leave ¾″ at the wall, pull it tight and face-nail it.
  10. Transitions at the doorways, then the trim — nailed to the wall or baseboard, never down into the floor.
Flooring & tile · Sheet S-11 · 03Tools (25)

Tools (25)

Must-have tools first, then the ones that help and the ones to rent for the day.

ToolNeedWhy
Tape measure (25 ft)Must haveThe red boxes every 16″ on the blade are stud spacing.
Carpenter's pencilMust haveFlat, doesn't roll away, marks rough lumber.
Chalk lineMust haveSnap the starting line and keep the rows straight
Moisture meterMust haveRead the boards and the subfloor before and during the wait
HygrometerGood to haveRoom humidity: 30–50% is the target
Straightedge (6 ft)Must haveCheck the subfloor for flat
Miter sawMust haveSquare end cuts and trim miters
Job-site table sawMust haveRip the last row to width
JigsawMust haveNotches around vents, pipes and door jambs
Jamb (undercut) sawMust haveUndercut door casings so the floor slides under
Oscillating multi-toolGood to haveUndercuts faster than a jamb saw
Hardwood flooring nailerRentDrives the cleats through the tongue at the right angle
Air compressor + hoseRentRuns the flooring nailer and the finish nailer
Finish nailer (15/16-ga)Must haveFace-nails the first and last rows
Cordless drill/driverMust havePre-drill face nails in hardwood
Flooring board jackGood to havePulls bowed boards tight before nailing
Rubber malletMust haveSeat boards with a scrap block, never the bare face
Pry barGood to havePull old shoe molding
Brad nailer (18-ga)Good to haveTrim; or hand-nail with a nail set
Nail setMust haveSinks finish-nail heads below the surface.
Caulk gunMust haveDispenses caulk and adhesive.
Knee padsMust haveFlooring and tile are all knees.
Safety glassesMust haveEvery cut, every nail, every time.
Hearing protectionMust haveNailers and saws are loud
N95 dust masksMust haveCutting dust
Flooring & tile · Sheet S-11 · 04Mistakes and how the math works

Mistakes and how the math works

Mistakes that cost a callback or a second trip

  • Skipping the moisture check: Boards laid wetter or drier than the subfloor cup, gap or buckle within a season. Meter both, and wait until they’re within 4% (2% for wide boards).
  • No expansion gap: Wood moves with the seasons. Leave ¾″ at every wall, pipe and cabinet, hidden by the trim.
  • Boards from one box at a time: Color and length bunch up in patches. Open several boxes and mix them as you go.
  • Boards along the joists: Nailed boards run across the floor joists (or diagonally) over a single-layer subfloor, or the floor sags between joists (NWFA).

What the calculator assumes

  • +10% for straight layouts, +15% for diagonal, rounded up to whole boxes.
  • Expansion gap: ¾″ for ¾″ solid (NWFA).
  • Moisture (NWFA): subfloor 12% or less; boards within 4% of it (2% for boards 3″ and wider); HVAC on 5 days before; 60–80 °F and 30–50% humidity. No set number of days to wait — the meter decides.
  • Fasteners (NWFA): 1½–2″ cleats or staples every 8–10″ on strip under 3″, 6–8″ on wider boards, 1–3″ from the ends; #15 felt with 4″ overlaps.
  • Subfloor (NWFA): at least 5/8″ plywood or 23/32″ OSB on joists 16″ apart; boards across the joists.
Flooring & tile · Sheet S-11 · 05Code, permits and safety

Code, permits and safety

The Sheet sets its code notes for the job's state or province. These are New Jersey's and Ontario's; the code reference has more. Always confirm with your building department.

  • Permits: a job like this usually needs none, but towns set their own rules. Ask your building department if you're not sure.
Flooring & tile · Sheet S-11 · 06Questions

Questions

What materials do I need to install hardwood or laminate flooring?

For the worked example, a 14′ × 12′ floor, the Sheet counts 8 lines with waste included, starting with solid hardwood flooring ¾″ (10 boxes), asphalt felt #15 (1 roll), flooring cleats or staples (2 boxes of 1,000), finish nails (15 or 16-ga) (1 box). Each line's math is in the table above. Put in your own sizes in the wood floor calculator and every line is counted again.

How long does it take to install hardwood or laminate flooring, and can I do it myself?

About 12 to 18 hours for the worked example, in 10 steps. StudSheet stamps it DIY OK: you can do this.

What tools do I need to install hardwood or laminate flooring?

25 in all. The must-haves start with tape measure (25 ft), carpenter's pencil, chalk line, moisture meter, straightedge (6 ft), miter saw. On the Sheet you mark each one as owned, to buy or to rent.

Flooring & tile · Sheet S-11 · 07Ask about it

Ask about it

Stuck while you install hardwood or laminate flooring? Ask in the Hardwood and laminate group of the StudSheet community with this Sheet attached. Homeowners who've done it and verified pros answer, and anyone can read it.

Flooring & tile · Sheet S-11 · 08More flooring & tile Sheets

More flooring & tile Sheets

  • Flooring for contractors: run this takeoff at your own prices, send the estimate, and get it signed and the deposit paid.
  • Carpet a room (14′ × 12′ room): Tack strip, pad, seams and stretching — the full stretch-in install.
  • Install vinyl plank flooring (14′ × 12′ floor): Click-together LVP: boxes, trim, transitions and the gaps that matter.
  • Tile a floor (8′ × 5′ bathroom): Backer, thinset, tile and grout sized to your tile — bathroom, kitchen or entry, with the toilet reset when there is one.
  • Tile a kitchen backsplash (12′ of backsplash, 18″ tall): Tile, adhesive, grout, edge trim and outlet extenders for the wall between the counter and the cabinets, counted from the run and height.
  • Tile a shower or tub surround (5′ tub surround, tiled to 7′): Backer board, waterproofing, tile, thinset and grout for a tub surround or a walk-in shower — every seam, corner and pipe sealed.
  • Carpet stairs (13 steps, 3′ wide): Carpet, pad and tack strip cut step by step — waterfall or wrapped (Hollywood) — with the pile running down the stairs and the landing included.