Sheet S-30 · Tile a shower or tub surround
5′ tub surround, tiled to 7′
- Tile
- 66sq ft, walls
- Membrane
- 2gal, liquid membrane
- Thinset
- 150 lb bag
- Grout
- 110 lb bag
Tools you need
- Notched trowel
- Margin trowel
- ½″ drill + mixing paddle
- 5-gal buckets (2)
- Grout float
- Grout sponges + 2 buckets
26 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 5 sheets | Cement backer board ½″ (3×5)½″, 3×5 sheets | 57.5 sq ft of wall + 10% ÷ 15 sq ft per sheet. |
| ≈225 screws | Cement board screws 1¼″ | A screw every 8″ into the studs — about 45 a sheet. |
| 1 roll | Alkali-resistant mesh tape 2″2″ × 150 ft | Mesh tape bedded in thinset on every board seam. |
| 2 × 1 gal pail | Liquid waterproofing membranetwo coats | 57.5 sq ft of wall + 10% ÷ about 55 sq ft per gallon for both coats = 1.15 gal; the cheaper mix of pails. |
| 1 roll | Membrane reinforcing fabricabout 75 ft rolls | 26′ 10″ of corners, seams at the tub and around the niche: fabric bedded in the first coat. |
| 1 | Roller covers 9″⅜″ nap | Rolls the membrane on; a brush does the corners. |
| 1 niche | Prefab shower nicheabout 12″ × 20″ | Set between two studs, banded into the membrane; its sill slopes out. |
| 2 boards | 2×42×4 × 8′ | Blocking between the studs for grab bars and above and below each niche. |
| 197 tiles (66 sq ft) | Wall tile4×12, porcelain | 57.5 sq ft of wall (10′ × 5′ 9″) + 1.5 sq ft of niche returns, + 10% for cuts = 195, + 2 spares. Buy from one lot number. |
| 1 bag | Modified thinset mortar, 50 lb50 lb bag | 59 sq ft ÷ 80 sq ft a bag with a ¼″ × ¼″ square notch. Modified thinset over cement board. |
| 1 × 10 lb bag | Sanded grout1/8″ joints | Joint volume: (4+12)″ × 1/8″ wide × 5/16″ deep per tile ≈ 1.88 cu in per sq ft × 59 sq ft ≈ 8.3 lb with 15% extra. Sanded for joints ⅛″ and up. |
| 1 | Grout sealerpenetrating | Cement grout soaks up water and soap: seal it once it cures (see the bag), and again every year or two. |
| 1 bag | Tile spacers1/8″ | Even joints, and the ⅛″ gap at the tub or base and every corner. |
| 3 lengths | Metal tile edge trim8′ 2-1/2″ lengths, 5/16″ tall | The open edges: both sides (11′ 6″), the top of the tile (10′) ÷ 8′ 2-1/2″ lengths. Or bullnose to match the tile. |
| 1 tube | 100% silicone, color-matched100% silicone, color-matched, mildew-resistant | 21′ 6″ of joint (2 inside corners, the tub) + 15% at about 55 ft a 10.1 oz tube. Every change of plane gets silicone, not grout. |
| 1 pack | Contractor bags + duct tapeheavy contractor bags | Old tile, board and mortar are heavy: half-fill each bag. About 345 lb of debris. |
| 1 sheet | Plastic sheeting 9×12for the doorway | Tape plastic over the bathroom door and the vent while you tear out and cut. |
Sheet S-30 · Tile a shower or tub surround
1.52 m tub surround, tiled to 2.13 m
- Tile
- 6.1m², walls
- Membrane
- 7.6L, liquid membrane
- Thinset
- 122.7 kg bag
- Grout
- 14.5 kg bag
Tools you need
- Notched trowel
- Margin trowel
- 13 mm drill + mixing paddle
- 18.9 L buckets (2)
- Grout float
- Grout sponges + 2 buckets
26 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 5 sheets | Cement backer board 13 mm (3×5)13 mm, 3×5 sheets | 5.3 m² of wall + 10% ÷ 1.4 m² per sheet. |
| ≈225 screws | Cement board screws 32 mm | A screw every 203 mm into the studs — about 45 a sheet. |
| 1 roll | Alkali-resistant mesh tape 50 mm50 mm × 45.7 m | Mesh tape bedded in thinset on every board seam. |
| 2 × 3.78 L pail | Liquid waterproofing membranetwo coats | 5.3 m² of wall + 10% ÷ about 5.1 m² per 3.78 L for both coats = 4.4 L; the cheaper mix of pails. |
| 1 roll | Membrane reinforcing fabricabout 22.86 m rolls | 8.18 m of corners, seams at the tub and around the niche: fabric bedded in the first coat. |
| 1 | Roller covers 230 mm10 mm nap | Rolls the membrane on; a brush does the corners. |
| 1 niche | Prefab shower nicheabout 305 × 508 mm | Set between two studs, banded into the membrane; its sill slopes out. |
| 2 boards | 2×42×4 × 2.44 m | Blocking between the studs for grab bars and above and below each niche. |
| 197 tiles (6.1 m²) | Wall tile4×12, porcelain | 5.3 m² of wall (3.05 m × 1.75 m) + 0.1 m² of niche returns, + 10% for cuts = 195, + 2 spares. Buy from one lot number. |
| 1 bag | Modified thinset mortar, 22.7 kg22.7 kg bag | 5.5 m² ÷ 7.4 m² a bag with a 6 × 6 mm square notch. Modified thinset over cement board. |
| 1 × 4.5 kg bag | Sanded grout3 mm joints | Joint volume: (102 mm + 305 mm) × 3 mm wide × 8 mm deep per tile ≈ 331 cm³ per m² × 5.5 m² ≈ 3.8 kg with 15% extra. Sanded for joints 3 mm and up. |
| 1 | Grout sealerpenetrating | Cement grout soaks up water and soap: seal it once it cures (see the bag), and again every year or two. |
| 1 bag | Tile spacers3 mm | Even joints, and the 3 mm gap at the tub or base and every corner. |
| 3 lengths | Metal tile edge trim2.5 m lengths, 8 mm tall | The open edges: both sides (3.51 m), the top of the tile (3.05 m) ÷ 2.5 m lengths. Or bullnose to match the tile. |
| 1 tube | 100% silicone, color-matched100% silicone, color-matched, mildew-resistant | 6.55 m of joint (2 inside corners, the tub) + 15% at about 16.74 m a 300 mL tube. Every change of plane gets silicone, not grout. |
| 1 pack | Contractor bags + duct tapeheavy contractor bags | Old tile, board and mortar are heavy: half-fill each bag. About 156 kg of debris. |
| 1 sheet | Plastic sheeting 2.7 × 3.7 mfor the doorway | Tape plastic over the bathroom door and the vent while you tear out and cut. |