StudSheet Sheets Flooring & tile · Sheet S-30

Shower tile calculator

5′ tub surround, tiled to 7′: 66 sq ft of wall tile, 2 gal of waterproofing, and the backer board, thinset and grout. Backer board, waterproofing, tile, thinset and grout for a tub surround or a walk-in shower — every seam, corner and pipe sealed.

Free, no account needed. Type your own sizes and every line is counted again.

Worked example · feet and inches (New Jersey) or metric (Ontario)

Sheet S-30 · Tile a shower or tub surround

5′ tub surround, tiled to 7′

DIY OK
WALLS, UNFOLDEDend, back, end over the tub6′ code line5′ 9″10′ of wall1234
Tub surround
Tile
66sq ft, walls
Membrane
2gal, liquid membrane
Thinset
150 lb bag
Grout
110 lb bag

Tools you need

  • Notched trowel
  • Margin trowel
  • ½″ drill + mixing paddle
  • 5-gal buckets (2)
  • Grout float
  • Grout sponges + 2 buckets

26 tools on the Sheet, each marked own, buy or rent

What to buy 17 lines, each with its math
BuyItemHow we got this
5 sheetsCement backer board ½″ (3×5)½″, 3×5 sheets57.5 sq ft of wall + 10% ÷ 15 sq ft per sheet.
≈225 screwsCement board screws 1¼″A screw every 8″ into the studs — about 45 a sheet.
1 rollAlkali-resistant mesh tape 2″2″ × 150 ftMesh tape bedded in thinset on every board seam.
2 × 1 gal pailLiquid waterproofing membranetwo coats57.5 sq ft of wall + 10% ÷ about 55 sq ft per gallon for both coats = 1.15 gal; the cheaper mix of pails.
1 rollMembrane reinforcing fabricabout 75 ft rolls26′ 10″ of corners, seams at the tub and around the niche: fabric bedded in the first coat.
1Roller covers 9″⅜″ napRolls the membrane on; a brush does the corners.
1 nichePrefab shower nicheabout 12″ × 20″Set between two studs, banded into the membrane; its sill slopes out.
2 boards2×42×4 × 8′Blocking between the studs for grab bars and above and below each niche.
197 tiles (66 sq ft)Wall tile4×12, porcelain57.5 sq ft of wall (10′ × 5′ 9″) + 1.5 sq ft of niche returns, + 10% for cuts = 195, + 2 spares. Buy from one lot number.
1 bagModified thinset mortar, 50 lb50 lb bag59 sq ft ÷ 80 sq ft a bag with a ¼″ × ¼″ square notch. Modified thinset over cement board.
1 × 10 lb bagSanded grout1/8″ jointsJoint volume: (4+12)″ × 1/8″ wide × 5/16″ deep per tile ≈ 1.88 cu in per sq ft × 59 sq ft ≈ 8.3 lb with 15% extra. Sanded for joints ⅛″ and up.
1Grout sealerpenetratingCement grout soaks up water and soap: seal it once it cures (see the bag), and again every year or two.
1 bagTile spacers1/8″Even joints, and the ⅛″ gap at the tub or base and every corner.
3 lengthsMetal tile edge trim8′ 2-1/2″ lengths, 5/16″ tallThe open edges: both sides (11′ 6″), the top of the tile (10′) ÷ 8′ 2-1/2″ lengths. Or bullnose to match the tile.
1 tube100% silicone, color-matched100% silicone, color-matched, mildew-resistant21′ 6″ of joint (2 inside corners, the tub) + 15% at about 55 ft a 10.1 oz tube. Every change of plane gets silicone, not grout.
1 packContractor bags + duct tapeheavy contractor bagsOld tile, board and mortar are heavy: half-fill each bag. About 345 lb of debris.
1 sheetPlastic sheeting 9×12for the doorwayTape plastic over the bathroom door and the vent while you tear out and cut.
Flooring & tile · Sheet S-30 · 01What to buy (5′ tub surround, tiled to 7′)

What to buy (5′ tub surround, tiled to 7′)

Every line shows the quantity to buy and how StudSheet got it: the spacing, the waste and the package size, so you can check it before the supply house or the quote.

BuyMaterialHow StudSheet counts itWhat it is for
5 sheetsCement backer board ½″ (3×5) (½″, 3×5 sheets)57.5 sq ft of wall + 10% ÷ 15 sq ft per sheet.Wall backer for tub and shower tile: doesn’t rot or swell. Screws every 8″, seams taped.
≈225 screwsCement board screws 1¼″A screw every 8″ into the studs — about 45 a sheet.Coated screws with ribbed heads.
1 rollAlkali-resistant mesh tape 2″ (2″ × 150 ft)Mesh tape bedded in thinset on every board seam.For backer-board seams.
2 × 1 gal pailLiquid waterproofing membrane (two coats)57.5 sq ft of wall + 10% ÷ about 55 sq ft per gallon for both coats = 1.15 gal; the cheaper mix of pails.Rolled or brushed on in two coats (RedGard or Hydro Ban type): a seamless waterproof skin over cement board. About 55 sq ft per gallon for the full two coats.
1 rollMembrane reinforcing fabric (about 75 ft rolls)26′ 10″ of corners, seams at the tub and around the niche: fabric bedded in the first coat.Fabric bedded in the liquid membrane at corners, changes of plane and around pipes, where walls move.
1Roller covers 9″ (⅜″ nap)Rolls the membrane on; a brush does the corners.Nap length depends on wall texture.
1 nichePrefab shower niche (about 12″ × 20″)Set between two studs, banded into the membrane; its sill slopes out.A waterproof foam niche (about 12″ × 20″) set between two studs and banded into the membrane.
2 boards2×4 (2×4 × 8′)Blocking between the studs for grab bars and above and below each niche.Framing lumber, actually 1½″ × 3½″.
197 tiles (66 sq ft)Wall tile (4×12, porcelain)57.5 sq ft of wall (10′ × 5′ 9″) + 1.5 sq ft of niche returns, + 10% for cuts = 195, + 2 spares. Buy from one lot number.Ceramic or porcelain tile for walls, backsplashes and showers (the floor tile Sheet lists floor tile).
1 bagModified thinset mortar, 50 lb (50 lb bag)59 sq ft ÷ 80 sq ft a bag with a ¼″ × ¼″ square notch. Modified thinset over cement board.Cement-based adhesive that bonds tile.
1 × 10 lb bagSanded grout (1/8″ joints)Joint volume: (4+12)″ × 1/8″ wide × 5/16″ deep per tile ≈ 1.88 cu in per sq ft × 59 sq ft ≈ 8.3 lb with 15% extra. Sanded for joints ⅛″ and up.For joints ⅛″ and wider.
1Grout sealer (penetrating)Cement grout soaks up water and soap: seal it once it cures (see the bag), and again every year or two.Slows staining in cement grout.
1 bagTile spacers (1/8″)Even joints, and the ⅛″ gap at the tub or base and every corner.Keep joints even.
3 lengthsMetal tile edge trim (8′ 2-1/2″ lengths, 5/16″ tall)The open edges: both sides (11′ 6″), the top of the tile (10′) ÷ 8′ 2-1/2″ lengths. Or bullnose to match the tile.An L-shaped metal edge (Schluter JOLLY or Schiene type) set in the thinset under the last row: a clean, chip-proof open edge.
1 tube100% silicone, color-matched (100% silicone, color-matched, mildew-resistant)21′ 6″ of joint (2 inside corners, the tub) + 15% at about 55 ft a 10.1 oz tube. Every change of plane gets silicone, not grout.Flexible movement joint at walls and the tub.
1 packContractor bags + duct tape (heavy contractor bags)Old tile, board and mortar are heavy: half-fill each bag. About 345 lb of debris.For rolling up and hauling the old carpet.
1 sheetPlastic sheeting 9×12 (for the doorway)Tape plastic over the bathroom door and the vent while you tear out and cut.Covers furniture.

In Canada (1.52 m tub surround, tiled to 2.13 m)

Set to Canada, the Sheet works the job out again for Ontario: metric sizes, bag sizes, the frost depth and the code notes. It doesn't just convert feet to meters. The first lines:

  • 5 sheets, Cement backer board 13 mm (3×5): 5.3 m² of wall + 10% ÷ 1.4 m² per sheet.
  • ≈225 screws, Cement board screws 32 mm: A screw every 203 mm into the studs — about 45 a sheet.
  • 1 roll, Alkali-resistant mesh tape 50 mm: Mesh tape bedded in thinset on every board seam.
  • 2 × 3.78 L pail, Liquid waterproofing membrane: 5.3 m² of wall + 10% ÷ about 5.1 m² per 3.78 L for both coats = 4.4 L; the cheaper mix of pails.
  • 1 roll, Membrane reinforcing fabric: 8.18 m of corners, seams at the tub and around the niche: fabric bedded in the first coat.
  • 1, Roller covers 230 mm: Rolls the membrane on; a brush does the corners.
Flooring & tile · Sheet S-30 · 02The steps, in order

The steps, in order

  1. Shut off the water at the valve or the main, then tear out to the studs and check them for straightness and rot.
  2. Add blocking for grab bars, frame and set the niche.
  3. Backer: hang ½″ cement board ¼″ above the tub flange, screws every 8″, seams taped with mesh and thinset.
  4. Waterproof: bed fabric in the corners, the tub seam, the niche and around the pipes, then roll coat 1; once it changes color, roll coat 2 crosswise — each 50–60 wet mils, up to the top of the tile.
  5. Set tile: the walls from a level ledger one row up from the tub, with a ¼″ × ¼″ square notch; leave ⅛″ at every change of plane.
  6. Grout: after 24 h, pack the joints with cement grout and clean the haze; keep grout out of the corners and the tub joint.
  7. Caulk: silicone every inside corner and the tub joint.
  8. Seal: once it has cured, seal the grout (see the bag); trim plates and the shower head back on.
Flooring & tile · Sheet S-30 · 03Tools (26)

Tools (26)

Must-have tools first, then the ones that help and the ones to rent for the day.

ToolNeedWhy
Notched trowelMust have¼″ × ¼″ square notch
Margin trowelMust haveNarrow flat trowel for mixing and back-buttering.
½″ drill + mixing paddleMust haveThinset mixed by hand stays lumpy
5-gal buckets (2)Must haveTwo: one to mix, one to rinse
Grout floatMust haveRubber float that packs grout into joints.
Grout sponges + 2 bucketsMust haveCleans haze. One bucket to rinse, one of clean water.
4-ft levelMust haveThe ledger line and plumb walls
Cross-line laser levelGood to haveOne level line around all three walls
Straightedge (6 ft)Must haveChecks the walls are flat before the tile goes up
Cement-board scoring knifeMust haveScores and snaps cement board
Utility knife + bladesMust haveScores drywall and vinyl plank, trims pad. Swap blades often.
Cordless drill/driverMust haveScrews the backer off
Hole saw kitMust haveClean holes in the backer for the valve and pipes
9″ roller frameMust haveRolls the membrane on
Wet-film thickness gaugeGood to haveChecks each coat is thick enough
Wet tile sawRentClean cuts in porcelain, and the notches around the valve
Tile snap cutterMust haveFast straight cuts
Diamond hole bits (tile)Must haveRound holes for the valve, the spout and the shower arm
Caulk gunMust haveDispenses caulk and adhesive.
Demolition hammerGood to haveBreaks old tile and mortar off fast
Pry barMust havePulls the old board off the studs
Shop vacMust haveDust and debris
Knee padsMust haveFlooring and tile are all knees.
Safety glassesMust haveEvery cut, every nail, every time.
Work glovesMust haveThinset and grout are caustic
Half-face respirator (P100)Must haveSilica dust from cutting and demolition
Flooring & tile · Sheet S-30 · 04Mistakes and how the math works

Mistakes and how the math works

Mistakes that cost a callback or a second trip

  • Drywall behind the tile: Even green board turns to mush behind shower tile. Cement-type backer, or foam board, with a membrane.
  • Two vapor barriers: Poly behind the board and a membrane in front trap water in the board. One or the other.
  • Membrane too thin: A liquid membrane only works at full thickness: two coats, checked with a wet-film gauge or the color change.
  • Grout in the corners: Changes of plane move and crack grout. Silicone in every corner and at the tub.
  • Tile over the tub flange: The backer and tile stop just above the flange, and the joint gets silicone — tile pushed onto the flange cracks and leaks.

What the calculator assumes

  • Tub surround: the tile starts at the tub’s rim, taken as 15″ above the floor.
  • Backer: ½″ cement board in 3×5 sheets (15 sq ft), +10%, a screw every 8″; foam board ½″ × 32″ × 48″, +10%.
  • Liquid membrane: about 55 sq ft per gallon for both coats at 50–60 wet mils (RedGard), +10%. Sheet membrane: +15% for the 2″ overlaps and corners.
  • Tile: +10% for cuts (15% for large format), + 2 spares; mosaic floor sheets +15%. Niche returns about 1.5 sq ft each.
  • Thinset per 50 lb bag: about 95 sq ft with a V-notch, 80 sq ft with ¼″ × ¼″, 40 sq ft with ½″ × ½″, +20% back-buttering; unmodified over sheet membranes and foam board.
  • Grout: joint volume from the tile size, joint and thickness, ≈ 0.065 lb per cu in, +15%.
  • Silicone: about 55 ft a 10.1 oz tube at a 3/16″ bead (DAP), +15%.
Flooring & tile · Sheet S-30 · 05Code, permits and safety

Code, permits and safety

The Sheet sets its code notes for the job's state or province. These are New Jersey's and Ontario's; the code reference has more. Always confirm with your building department.

  • Wet walls: what the code asks: IRC R307.2 (R327 in the 2024 IRC): in showers and at tubs with showers, the walls get a smooth, nonabsorbent surface to at least 6 ft above the floor. IRC R702.4.2: behind tile in tub and shower areas, cement, fiber-cement or glass-mat gypsum backer — not drywall, even moisture-resistant drywall.
  • Wet walls: the National Building Code: NBC 9.29.2.1: walls in showers get a waterproof finish to at least 1.8 m above the floor, and around tubs with showers to at least 1.2 m above the rim. 9.29.10.4: tile around tubs and showers goes over moisture-resistant backing. 9.29.10.5: the joint between the tile and the tub is caulked with mildew-resistant sealant. Confirm with your building department.
Flooring & tile · Sheet S-30 · 06Questions

Questions

What materials do I need to tile a shower or tub surround?

For the worked example, a 5′ tub surround, tiled to 7′, the Sheet counts 17 lines with waste included, starting with cement backer board ½″ (3×5) (5 sheets), cement board screws 1¼″ (≈225 screws), alkali-resistant mesh tape 2″ (1 roll), liquid waterproofing membrane (2 × 1 gal pail). Each line's math is in the table above. Put in your own sizes in the shower tile calculator and every line is counted again.

How long does it take to tile a shower or tub surround, and can I do it myself?

About 34 to 53 hours for the worked example, in 8 steps. StudSheet stamps it DIY OK: you can do this.

What tools do I need to tile a shower or tub surround?

26 in all. The must-haves start with notched trowel, margin trowel, ½″ drill + mixing paddle, 5-gal buckets (2), grout float, grout sponges + 2 buckets. On the Sheet you mark each one as owned, to buy or to rent.

Flooring & tile · Sheet S-30 · 07Ask about it

Ask about it

Stuck while you tile a shower or tub surround? Ask in the Tile showers and tub surrounds group of the StudSheet community with this Sheet attached. Homeowners who've done it and verified pros answer, and anyone can read it.

Flooring & tile · Sheet S-30 · 08More flooring & tile Sheets

More flooring & tile Sheets

  • Tile for contractors: run this takeoff at your own prices, send the estimate, and get it signed and the deposit paid.
  • Carpet a room (14′ × 12′ room): Tack strip, pad, seams and stretching — the full stretch-in install.
  • Install vinyl plank flooring (14′ × 12′ floor): Click-together LVP: boxes, trim, transitions and the gaps that matter.
  • Tile a floor (8′ × 5′ bathroom): Backer, thinset, tile and grout sized to your tile — bathroom, kitchen or entry, with the toilet reset when there is one.
  • Hardwood and laminate floors (14′ × 12′ floor): Install solid or engineered hardwood or laminate, or sand and refinish an old wood floor.
  • Tile a kitchen backsplash (12′ of backsplash, 18″ tall): Tile, adhesive, grout, edge trim and outlet extenders for the wall between the counter and the cabinets, counted from the run and height.
  • Carpet stairs (13 steps, 3′ wide): Carpet, pad and tack strip cut step by step — waterfall or wrapped (Hollywood) — with the pile running down the stairs and the landing included.
  • All 45 Sheets, across 16 trades.
  • Code reference: frost depths, guard heights, stairs, retaining walls.

Get the Sheet.

Open StudSheet
Coming soon on theApp StoreComing soon onGoogle Play