Sheet S-20 · Plumbing rough-in
3 fixtures
- Drain load
- 5DFU · IPC
- Branch
- 3″¼″ per foot
- Vents
- 1½″1½″ header
- Water
- ¾″ + ½″trunk + branches · 5 outlets
Tools you need
- Tape measure (25 ft)
- Carpenter's pencil
- 4-ft level
- Torpedo level
- Cordless drill/driver
- Right-angle drill
20 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 6 × 10′ lengths | PVC DWV pipe, 1½ in1½″ PVC DWV, Schedule 40 | vent for 1 toilet 6 ft + 1 lavatory 4 ft + vent for 1 lavatory 6 ft + 1 tub/shower 5 ft + vent for 1 tub/shower 6 ft + vent header 20 ft = 47 ft, + 10% for cuts → 6 × 10′. |
| 3 × 10′ lengths | PVC DWV pipe, 3 in3″ PVC DWV, Schedule 40 | 1 toilet 4 ft + branch 20 ft = 24 ft, + 10% for cuts → 3 × 10′. |
| 27 fittings | DWV fittings, 1½ in (PVC or ABS)1½″ PVC DWV | Allowance: the trap or bend, tees and elbows at each fixture (3–4), 3 per vent, a wye or combo per fixture on the branch, long sweeps, and a coupling between lengths. |
| 10 fittings | DWV fittings, 3 in (PVC or ABS)3″ PVC DWV | Allowance: the trap or bend, tees and elbows at each fixture (3–4), 3 per vent, a wye or combo per fixture on the branch, long sweeps, and a coupling between lengths. |
| 2 pint sets | PVC primer and cement (pint set) | About 130 joint-equivalents (a 3″ joint takes about 2½ times the cement of a 1½″ one); a pint does about 90 of the small ones. |
| 1 × 100′ coil | PEX-A tubing, ½ in½″ PEX-A | 5 branches × 6 ft = 30 ft, + 10% → 1 × 100′ coil. ½″ to every fixture (the codes allow ⅜″ for some — lavatories and toilets — but ½″ covers all). |
| 1 × 100′ coil | PEX-A tubing, ¾ in¾″ PEX-A | cold trunk 25 ft + hot trunk 25 ft = 50 ft, + 10% → 1 × 100′ coil. Sized for 3.6 WSFU → 7.4 gpm on Hunter’s curve, under 8 ft/s (¾″ minimum). |
| 15 fittings | PEX-A expansion fittings½–1″ | A tee and two elbows per outlet (5 outlets). |
| 41 rings | PEX-A expansion ringssized to the tubing | About 2½ tube ends per fitting (15) + 1 per stub-out (3). |
| 2 valves | Ball valve, ¾ in¾″ full port | Shutoff where each new trunk leaves the main, so the new work can be isolated. |
| 3 stub-outs | Stub-out elbows½″ | One per supply at sinks, lavatories, toilets and laundry tubs. |
| 3 caps | Test caps for stub-outs½″ | Caps the stub-outs for the water test and keeps them clean until trim-out. |
| 3 stops | Quarter-turn angle stops½″ × ⅜″ compression | 2 per sink, lavatory and laundry tub, 1 per toilet. Bought now, set at trim-out. |
| 1 valve | Tub/shower valve bodypressure-balance or thermostatic | One per tub/shower and shower: an individual shower valve must limit the temperature (ASSE 1016 or 1070). |
| 1 kit | Tub drain and overflowmatch the tub | Drain and overflow for each tub. |
| 1 flange | Closet flange3″ × 4″ | One per toilet, set to the finished floor height. |
| 1 trap | P-trap, 1½ in (DWV)1½″ | Tubs and showers: traps that go in at rough-in. |
| 1 adapter | Trap adapters, 1½ in1½″ | The wall stub for each sink, lavatory and laundry tub trap. |
| 1 cleanout | Cleanout fittings with plugs3″ | At the upper end of the branch (IPC 708: at the base of each stack and every 100 ft); add one at each change of direction over 135°. |
| 11 plates | Nail plates (steel)16-gauge | One where each drain (3), supply (5) and vent (3) passes a stud or plate within 1¼″ of its face. |
| 18 hangers | DWV pipe hangersfor PVC | One every 4′ on horizontal pipe (IPC Table 308.5). |
| 30 clips | Supply pipe clipsfor PEX-A | One every 2′ 8″ along 80 ft of water pipe (IPC Table 308.5). |
Sheet S-20 · Plumbing rough-in
3 fixtures
- Drain load
- 6fixture units · NPC
- Branch
- 3 in1 in 50 (2%)
- Vents
- 1½ in1½ in header
- Water
- ¾ in + ½ intrunk + branches · 5 outlets
Tools you need
- Tape measure (7.5 m)
- Carpenter's pencil
- 1.2 m level
- Torpedo level
- Cordless drill/driver
- Right-angle drill
20 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 5 × 3.66 m lengths | PVC DWV pipe, 1½ in1½ in PVC DWV, Schedule 40 | vent for 1 toilet 1.83 m + 1 lavatory 1.22 m + vent for 1 lavatory 1.83 m + 1 tub/shower 1.52 m + vent for 1 tub/shower 1.83 m + vent header 6.10 m = 14.33 m, + 10% for cuts → 5 × 3.66 m. |
| 3 × 3.66 m lengths | PVC DWV pipe, 3 in3 in PVC DWV, Schedule 40 | 1 toilet 1.22 m + branch 6.10 m = 7.32 m, + 10% for cuts → 3 × 3.66 m. |
| 26 fittings | DWV fittings, 1½ in (PVC or ABS)1½ in PVC DWV | Allowance: the trap or bend, tees and elbows at each fixture (3–4), 3 per vent, a wye or combo per fixture on the branch, long sweeps, and a coupling between lengths. |
| 10 fittings | DWV fittings, 3 in (PVC or ABS)3 in PVC DWV | Allowance: the trap or bend, tees and elbows at each fixture (3–4), 3 per vent, a wye or combo per fixture on the branch, long sweeps, and a coupling between lengths. |
| 2 473 mL can sets | PVC primer and cement (pint set)473 mL | About 128 joint-equivalents (a 3 in joint takes about 2½ times the cement of a 1½ in one); a 473 mL can does about 90 of the small ones. |
| 1 × 30.48 m coil | PEX-A tubing, ½ in½ in PEX-A | 5 branches × 1.83 m = 9.14 m, + 10% → 1 × 30.48 m coil. ½ in to every fixture (the codes allow ⅜ in for some — lavatories and toilets — but ½ in covers all). |
| 1 × 30.48 m coil | PEX-A tubing, ¾ in¾ in PEX-A | cold trunk 7.62 m + hot trunk 7.62 m = 15.24 m, + 10% → 1 × 30.48 m coil. Sized for 3.6 WSFU → 28 L/min on Hunter’s curve, under 2.4 m/s (¾ in minimum). |
| 15 fittings | PEX-A expansion fittings½–1 in | A tee and two elbows per outlet (5 outlets). |
| 41 rings | PEX-A expansion ringssized to the tubing | About 2½ tube ends per fitting (15) + 1 per stub-out (3). |
| 2 valves | Ball valve, ¾ in¾ in full port | Shutoff where each new trunk leaves the main, so the new work can be isolated. |
| 3 stub-outs | Stub-out elbows½ in | One per supply at sinks, lavatories, toilets and laundry tubs. |
| 3 caps | Test caps for stub-outs½ in | Caps the stub-outs for the water test and keeps them clean until trim-out. |
| 3 stops | Quarter-turn angle stops½ in × ⅜ in compression | 2 per sink, lavatory and laundry tub, 1 per toilet. Bought now, set at trim-out. |
| 1 valve | Tub/shower valve bodypressure-balance or thermostatic | One per tub/shower and shower: an individual shower valve must limit the temperature (ASSE 1016 or 1070; OBC 7.2.10.7). |
| 1 kit | Tub drain and overflowmatch the tub | Drain and overflow for each tub. |
| 1 flange | Closet flange3 in × 4 in | One per toilet, set to the finished floor height. |
| 1 trap | P-trap, 1½ in (DWV) | Tubs and showers: traps that go in at rough-in. |
| 1 adapter | Trap adapters, 1½ in | The wall stub for each sink, lavatory and laundry tub trap. |
| 1 cleanout | Cleanout fittings with plugs3 in | At the upper end of the branch (OBC 7.4.7: one every 15 m on a horizontal drain); add one at each change of direction over 135°. |
| 11 plates | Nail plates (steel)16-gauge | One where each drain (3), supply (5) and vent (3) passes a stud or plate within 32 mm of its face. |
| 19 hangers | DWV pipe hangersfor PVC | One every 1.20 m on horizontal pipe (OBC 7.3.4.5). |
| 31 clips | Supply pipe clipsfor PEX-A | One every 800 mm along 24.38 m of water pipe (OBC 7.3.4.5). |