Panel upgrade takeoff

100 A to 200 A service: 4/0 AWG Al conductors, a 40-space panel, 20 breakers and the grounding (2 rods). For electricians: panel, breakers, service cable, grounding, and the utility and permit steps.

Homeowners see what’s involved and can ask for quotes; contractors get the full Sheet with StudSheet Pro.

Worked example · feet and inches (New Jersey) or metric (Ontario)

Sheet S-19 · Panel or service upgrade

100 A to 200 A service

PRO JOB
SERVICE ONE-LINEutility → meter → disconnect → panel → grounding · not to scaleOUTSIDEINSIDEM200METER-MAINUTILITYservice headLUGS20 circuitsPANEL · 40 SPACES4/0 Al · 10′SPD6′ minwater pipe123456
Service one-line
Service
200 Afrom 100 A · overhead
Conductors
4/0 AWG Alor 2/0 AWG Cu
Panel
40spaces · main lug
Breakers
204 two-pole · 0 AFCI/GFCI

Tools you need

  • Non-contact voltage tester
  • Digital multimeter
  • Lockout/tagout kit
  • Insulating rubber gloves
  • Insulated screwdrivers (1000 V)
  • Torque screwdriver

19 tools on the Sheet, each marked own, buy or rent

What to buy 19 lines, each with its math
BuyItemHow we got this
20 ft — cut to lengthSEU cable 4/0-4/0-4/0, aluminumService head to the meter base, 4/0 AWG aluminum (2/0 AWG copper) (NEC 310.12). 20 ft is a guess — measure on site. A mast replaces it where the drop needs height.
1 headSE cable weatherheadAbove the point where the service drop attaches, with drip loops.
1 meter-mainMeter-main combination200 AMeter socket and the 200 A service breaker in one enclosure — the outdoor emergency disconnect (NEC 230.85). From the utility’s approved list.
20 ft — cut to lengthSER cable 4/0-4/0-4/0-2/0, aluminumFeeder, meter-main to the panel (4-wire SER): 10 ft + 6 ft for the ends + 10%. 4/0 AWG aluminum, or 2/0 AWG copper (NEC 310.12).
4 connectorsSE cable connectorsOne at each end of every SE cable run.
14 strapsSE cable strapsOutside within 12″ of the head and each enclosure and every 30″ (NEC 230.51); inside every 4½ ft.
1 panelMain lug panel (load center)200 A, 40 spaces40 spaces wanted → a 40-space panel — the moved circuits take 24. Main lug: the breaker ahead of it (the meter-main) protects it.
16 breakersBreaker, single-pole15 or 20 AOne per moved 120 V circuit, matched to its wire (14 AWG → 15 A, 12 AWG → 20 A), listed for the new panel.
4 breakersBreaker, 2-poleto match each circuitOne per moved 240 V circuit (range, dryer, water heater, AC…), matched to its wire.
1 surge protectorWhole-home surge protector (Type 1 or 2)Required with the new service equipment (NEC 230.67).
25 ftBare copper wire 6 AWGto the rods: 15 ft + 6 ft between them + slack. Lengths are a guess — measure on site.
20 ftBare copper wire 4 AWGto the water pipe: 15 ft + a jumper around the water meter. Lengths are a guess — measure on site.
2 rodsGround rod, copper-bonded5/8″ × 8 ftTwo rods at least 6 ft apart; one alone must test at 25 ohms or less (NEC 250.53(A)).
2 clampsGround rod clampOne per rod, listed for direct burial.
2 clampsWater pipe ground clampThe grounding conductor near where the pipe enters (within 5 ft, NEC 250.68(C)), and the jumper around the water meter.
1 terminationIntersystem bonding terminationCable TV, phone and satellite bonds land here (NEC 250.94).
1 tubeAntioxidant compoundAluminum service and feeder conductors at the lugs, where the lug maker calls for it.
1 packDuct sealSeal the service entrance and the conduit entries.
1 kitPanel labelsCircuit directory (NEC 408.4) and the emergency disconnect marking (230.85(E)).
Electrical · Sheet S-19 · 01What to buy (100 A to 200 A service)

What to buy (100 A to 200 A service)

Every line shows the quantity to buy and how StudSheet got it: the spacing, the waste and the package size, so you can check it before the supply house or the quote.

BuyMaterialHow StudSheet counts itWhat it is for
20 ft — cut to lengthSEU cable 4/0-4/0-4/0, aluminumService head to the meter base, 4/0 AWG aluminum (2/0 AWG copper) (NEC 310.12). 20 ft is a guess — measure on site. A mast replaces it where the drop needs height.200 A service-entrance cable.
1 headSE cable weatherheadAbove the point where the service drop attaches, with drip loops.Service head at the top of the SE cable, above the drip loop.
1 meter-mainMeter-main combination (200 A)Meter socket and the 200 A service breaker in one enclosure — the outdoor emergency disconnect (NEC 230.85). From the utility’s approved list.Meter socket and service disconnect in one outdoor enclosure — the outdoor emergency disconnect too. Utility-approved.
20 ft — cut to lengthSER cable 4/0-4/0-4/0-2/0, aluminumFeeder, meter-main to the panel (4-wire SER): 10 ft + 6 ft for the ends + 10%. 4/0 AWG aluminum, or 2/0 AWG copper (NEC 310.12).200 A service or feeder cable.
4 connectorsSE cable connectorsOne at each end of every SE cable run.Watertight connectors where SE cable enters the meter base and the panel.
14 strapsSE cable strapsOutside within 12″ of the head and each enclosure and every 30″ (NEC 230.51); inside every 4½ ft.Within 12″ of the service head and every 30″ outside (NEC 230.51); every 4½ ft inside.
1 panelMain lug panel (load center) (200 A, 40 spaces)40 spaces wanted → a 40-space panel — the moved circuits take 24. Main lug: the breaker ahead of it (the meter-main) protects it.Panel fed from a breaker ahead of it (meter-main or outdoor disconnect).
16 breakersBreaker, single-pole (15 or 20 A)One per moved 120 V circuit, matched to its wire (14 AWG → 15 A, 12 AWG → 20 A), listed for the new panel.Standard 120 V breaker listed for your panel (brand and type).
4 breakersBreaker, 2-pole (to match each circuit)One per moved 240 V circuit (range, dryer, water heater, AC…), matched to its wire.240 V breaker listed for your panel; takes two spaces.
1 surge protectorWhole-home surge protector (Type 1 or 2)Required with the new service equipment (NEC 230.67).At or next to the service equipment (NEC 230.67).
25 ftBare copper wire 6 AWGto the rods: 15 ft + 6 ft between them + slack. Lengths are a guess — measure on site.Grounding electrode conductor to rods, or a bonding jumper.
20 ftBare copper wire 4 AWGto the water pipe: 15 ft + a jumper around the water meter. Lengths are a guess — measure on site.Grounding electrode conductor or water pipe bond for a 200 A service.
2 rodsGround rod, copper-bonded (5/8″ × 8 ft)Two rods at least 6 ft apart; one alone must test at 25 ohms or less (NEC 250.53(A)).5/8″ × 8 ft in the US (3 m × 15.8 mm in Canada), driven full length.
2 clampsGround rod clampOne per rod, listed for direct burial.Bronze acorn clamp listed for direct burial.
2 clampsWater pipe ground clampThe grounding conductor near where the pipe enters (within 5 ft, NEC 250.68(C)), and the jumper around the water meter.Listed clamp for the grounding conductor or bonding jumper on metal water pipe.
1 terminationIntersystem bonding terminationCable TV, phone and satellite bonds land here (NEC 250.94).Bonding point for cable TV, phone and satellite grounds at the service (NEC 250.94).
1 tubeAntioxidant compoundAluminum service and feeder conductors at the lugs, where the lug maker calls for it.For aluminum conductors at the lugs.
1 packDuct sealSeal the service entrance and the conduit entries.Seals around the service entrance and conduit entries.
1 kitPanel labelsCircuit directory (NEC 408.4) and the emergency disconnect marking (230.85(E)).Circuit directory card and the emergency disconnect marking (red, white letters, NEC 230.85).

In Canada (100 A to 200 A service)

Set to Canada, the Sheet works the job out again for Ontario: metric sizes, bag sizes, the frost depth and the code notes. It doesn't just convert feet to meters. The first lines:

  • 6.10 m — cut to length, SEU cable 4/0-4/0-4/0, aluminum: Service head to the meter base, 4/0 AWG aluminum (2/0 AWG copper). 6.10 m is a guess — measure on site. A mast replaces it where the drop needs height.
  • 1 head, SE cable weatherhead: Above the point where the service drop attaches, with drip loops.
  • 1 meter-main, Meter-main combination: Meter socket and the 200 A service breaker in one enclosure. From the utility’s approved list.
  • 6.10 m — cut to length, SER cable 4/0-4/0-4/0-2/0, aluminum: Feeder, meter-main to the panel (4-wire SER): 3.05 m + 1.83 m for the ends + 10%. 4/0 AWG aluminum, or 2/0 AWG copper.
  • 4 connectors, SE cable connectors: One at each end of every SE cable run.
  • 14 straps, SE cable straps: Outside every 750 mm and within 300 mm of the head and each enclosure; inside every 1.5 m.
Electrical · Sheet S-19 · 02The order of work, for the licensed pro

The order of work, for the licensed pro

  1. Load calculation (NEC Article 220): confirm the service size.
  2. Apply to the utility for the service change; confirm the meter base and the disconnect date.
  3. Pull the electrical permit (electrical subcode) from the town’s construction office.
  4. Order the utility-approved meter-main, the panel and a breaker for every circuit.
  5. Trace and tag every circuit before the old panel comes out.
  6. Utility disconnect day: set the service equipment, the grounding electrode system and the bonding.
  7. Move every circuit to its new breaker; torque every lug and terminal to the label.
  8. Service inspection, then the utility reconnects and sets the meter.
  9. Label the panel directory and the emergency disconnect.
  10. Final inspection; give the client the approval.
Electrical · Sheet S-19 · 03Tools (19)

Tools (19)

Must-have tools first, then the ones that help and the ones to rent for the day.

ToolNeedWhy
Non-contact voltage testerMust haveProve the service dead after the utility disconnects
Digital multimeterMust haveVerify dead; check voltage at reconnection
Lockout/tagout kitMust haveLock out the disconnect while you work
Insulating rubber glovesMust haveRated gloves near anything that could still be live
Insulated screwdrivers (1000 V)Must haveBreaker and bar terminals
Torque screwdriverMust haveLug and terminal torque from the labels (NEC 110.14(D))
Nut driver setMust haveDrives hex-head screws on panel covers, ground screws and equipment.
Cable cutterMust haveCut SE and feeder cable clean
NM cable stripperGood to haveStrip the SE cable jacket
Knockout punch setMust haveKnockouts for the SE connectors and conduit
Step drill bitGood to haveSmall holes in enclosures
SDS rotary hammerRentWith a ground-rod driver bit: drives the rods
Cordless drill/driverMust haveDrills holes, drives screws, mixes small batches.
Wire strippersMust haveStrips insulation at the right gauge without nicking the copper.
Lineman’s pliersMust haveHeavy pliers that cut, twist and pull wire.
Clamp meterGood to haveCheck the loads on each leg after reconnection
8-ft ladder or rolling scaffoldMust haveReach the service head and the drop attachment
Safety glassesMust haveEvery cut, every nail, every time.
Work glovesMust haveKnockouts and cut cable armor are sharp
Electrical · Sheet S-19 · 04Mistakes and how the math works

Mistakes and how the math works

Mistakes that cost a callback or a second trip

  • A meter base the utility won’t accept: Each utility has an approved list; the wrong socket means a second disconnect day.
  • Sizing from the panel on sale: The service size comes from the load calculation, not from what’s in stock.
  • Loose aluminum lugs: Under-torqued aluminum terminations overheat: torque to the label and use the compound where the lug calls for it.
  • Neutral and ground bonded in the inside panel: With the service disconnect outside, the inside panel keeps neutrals and grounds apart — a common inspection failure.
  • One ground rod: A single rod needs a 25-ohm test to stand alone; most crews drive the second rod instead (NEC 250.53(A)(2)).
  • No working space: A panel behind the washer or in a closet fails: 30″ × 36″ clear in front (NEC 110.26).

What the calculator assumes

  • Service conductors: 83% of the rating at 75 °C for a one-family service (NEC 310.12): 100 A → 4 Cu / 2 Al, 150 A → 1 / 2/0, 200 A → 2/0 / 4/0, 400 A → 400 / 600 kcmil.
  • Grounding electrode conductor by the service conductor (NEC Table 250.66); 6 AWG copper is enough to rods (250.66(A)), 4 AWG to rebar (250.66(B)).
  • Rods: 8 ft, two at least 6 ft apart unless one tests at 25 ohms or less (NEC 250.53(A)); a metal water pipe electrode is always supplemented (250.53(D)).
  • NEC 2020 and later: outdoor emergency disconnect (230.85) and surge protection at the service (230.67).
  • Assumed lengths: 20 ft from the service head to the meter (overhead), 15 ft to the first rod and 15 ft to the water pipe — measure on site.
  • The load calculation is the electrician’s; this Sheet doesn’t size the service.
  • Labor: typical crew hours for a service change in the same location; relocation, a long run or a second panel add to it. Your crew’s numbers win.
Electrical · Sheet S-19 · 05Code, permits and safety

Code, permits and safety

The Sheet sets its code notes for the job's state or province. These are New Jersey's and Ontario's; the code reference has more. Always confirm with your building department.

  • Licensed electrical work: permit, utility and inspection: A service change needs an electrical permit (the electrical subcode) from your town’s construction office, filed by an electrical contractor licensed by the NJ Board of Examiners of Electrical Contractors — the license number and seal go on the application. The owner of a single-family home may do electrical work on the home they own under a homeowner permit (N.J.A.C. 5:23-2.15), inspected the same way. The utility has its own steps: the service application, its approved meter base, and the disconnect and reconnect appointment. Rules change — your town’s construction office has the last word.
  • Code: NEC 2020: New Jersey enforces the NEC 2020 (N.J.A.C. 5:23-3.16, with New Jersey’s changes). Towns can amend it. Rules change — your town’s construction office has the last word.
  • The load calculation decides the service size: This Sheet lists the work for the size you picked; it doesn’t size the service. Run the load calculation first (NEC Article 220: the standard method, or the optional method for a dwelling).
  • Talk to the utility before you order: Ask for its service requirements: the approved meter socket (some utilities supply it), the meter location, who owns the service drop and its attachment point, and the date to disconnect and reconnect. Many utilities reconnect only after the inspector releases the service.
  • Outdoor emergency disconnect (NEC 230.85): One- and two-family homes need an emergency disconnect outdoors, readily accessible: a meter-main, a service disconnect outside, or a listed disconnect ahead of the service disconnect. The meter-main’s breaker is it. Mark it “EMERGENCY DISCONNECT” (red, white letters) as 230.85(E) words it for its type.
  • Surge protection (NEC 230.67): A Type 1 or Type 2 surge protective device in or right next to the service equipment — required whenever the service equipment is replaced.
  • Service conductors: For a one-family service, 83% of the rating at 75 °C (NEC 310.12): 200 A → 4/0 AWG aluminum (180 A) or 2/0 AWG copper (175 A).
  • Grounding electrodes and bonding: Bond every electrode that’s there into one system (250.50): the metal water pipe (10 ft or more in the ground, always supplemented, 250.53(D)), two 8 ft rods at least 6 ft apart, unless one rod tests at 25 ohms or less (NEC 250.53(A)). Conductors: 4 AWG copper to the water pipe (Table 250.66), 6 AWG to the rods (250.66(A)). Bond the interior metal water piping (250.104(A)), gas piping through the equipment ground of the circuit most likely to energize it (250.104(B)), and install an intersystem bonding termination for cable, phone and satellite (250.94).
  • AFCI and GFCI for the moved circuits: New Jersey deleted the AFCI rule for extended branch circuits (210.12(D)), so moving the panel doesn’t trigger it there. Receptacles you replace where GFCI is now required get GFCI protection (406.4(D)(3)).
  • The inside panel is fed like a subpanel: With the service disconnect in the meter-main, the run to the inside panel is a feeder: four wires, neutral and equipment grounds kept separate in the inside panel (NEC 250.24(A)(5), 250.142(B)).
  • Where the panel can go: Working space 30″ wide and 36″ deep in front, 6½ ft high (NEC 110.26); never in a bathroom or a clothes closet (240.24(D), (E)).
  • Code: Ontario Electrical Safety Code 2024: Ontario enforces the 2024 Ontario Electrical Safety Code (CEC 2024 with Ontario amendments, in force May 1, 2025). The Sheet follows the CEC 2024 rules; check your province’s amendments.
Electrical · Sheet S-19 · 06Questions

Questions

What materials do I need to upgrade to a 200 amp panel?

For the worked example, a 100 A to 200 A service, the Sheet counts 19 lines with waste included, starting with sEU cable 4/0-4/0-4/0, aluminum (20 ft — cut to length), sE cable weatherhead (1 head), meter-main combination (1 meter-main), sER cable 4/0-4/0-4/0-2/0, aluminum (20 ft — cut to length). Each line's math is in the table above. Put in your own sizes in the panel upgrade calculator and every line is counted again.

How long does it take to upgrade to a 200 amp panel, and can I do it myself?

About 17 to 26 hours for the worked example, in 10 steps. StudSheet stamps it PRO JOB: hire this out (pros get the full Sheet).

What tools do I need to upgrade to a 200 amp panel?

19 in all. The must-haves start with non-contact voltage tester, digital multimeter, lockout/tagout kit, insulating rubber gloves, insulated screwdrivers (1000 v), torque screwdriver. On the Sheet you mark each one as owned, to buy or to rent.

Electrical · Sheet S-19 · 07Ask about it

Ask about it

Stuck while you upgrade to a 200 amp panel? Ask in the Panels and service upgrades group of the StudSheet community with this Sheet attached. Homeowners who've done it and verified pros answer, and anyone can read it.