Sheet S-09 · Hang and finish drywall
14′ × 12′ room
- Sheets
- 214×8
- Board
- 533sq ft to cover
- Compound
- 2pails
- Finish
- L43 coats
Tools you need
- Tape measure (25 ft)
- Carpenter's pencil
- Stud finder
- Chalk line
- Utility knife + blades
- Drywall T-square
28 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 15 sheets | Drywall ½″4×8 sheets | Walls, laid out wall by wall: 4 walls (2 × 14′ and 2 × 12′), 2 rows across the studs: 8 full + 6 cut for the row ends = 14. Offcuts are reused where they fit; doors and windows are cut out of full sheets. + 1 spare for breakage (about 5%). Covers 365 sq ft. |
| 6 sheets | Lightweight drywall ½″4×8 sheets | Ceiling: 3 rows across the joists, 14′ long: 3 full + 3 cut for the row ends = 6. Covers 168 sq ft. |
| ≈693 screws (3 lb) | Drywall screws, coarse thread1¼″ coarse thread | 15 wall sheets × 28 (one every 16″ on each stud) + 6 ceiling sheets × 35 (one every 12″ on each joist) + 10% for drops and strips. ½″ board takes 1¼″ screws — at least ⅝″ into the wood (IRC R702.3.6). About 250 per lb. |
| 2 pails | All-purpose joint compound4.5-gal pail (≈62 lb) | 533 sq ft of board × 10 gal per 1,000 sq ft for Level 4 (tape + 2 coats) = 5.3 gal (USG: about 9.4–10 gal per 1,000 sq ft for a three-coat job). |
| 1 roll | Paper joint tape250 ft roll | 197 ft: about 370 ft per 1,000 sq ft of board (USG), seams and inside corners. |
| 2 gallons | Drywall primer (PVA)1 coat | 533 sq ft ÷ 300 sq ft/gal = 1.78 gal. Seals the paper and the compound so the paint dries evenly. |
| 1 pack | Drywall sanding screens120–150 grit, 10-pack | About one pack per 600 sq ft of board: a light pass after each coat dries, never through to the paper. |
Sheet S-09 · Hang and finish drywall
4.27 m × 3.66 m room
- Sheets
- 214×8
- Board
- 49.5m² to cover
- Compound
- 2pails
- Finish
- L43 coats
Tools you need
- Tape measure (7.5 m)
- Carpenter's pencil
- Stud finder
- Chalk line
- Utility knife + blades
- Drywall T-square
28 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 15 sheets | Drywall 13 mm4×8 sheets | Walls, laid out wall by wall: 4 walls (2 × 4.27 m and 2 × 3.66 m), 2 rows across the studs: 8 full + 6 cut for the row ends = 14. Offcuts are reused where they fit; doors and windows are cut out of full sheets. + 1 spare for breakage (about 5%). Covers 33.9 m². |
| 6 sheets | Lightweight drywall 13 mm4×8 sheets | Ceiling: 3 rows across the joists, 4.27 m long: 3 full + 3 cut for the row ends = 6. Covers 15.6 m². |
| ≈693 screws (1.4 kg) | Drywall screws, coarse thread32 mm coarse thread | 15 wall sheets × 28 (one every 400 mm on each stud) + 6 ceiling sheets × 35 (one every 300 mm on each joist) + 10% for drops and strips. 13 mm board takes 32 mm screws — at least 15 mm into the wood (NBC 9.29.5.5). About 550 per kg. |
| 2 pails | All-purpose joint compound17 L pail (≈28 kg) | 49.5 m² of board × 0.41 L per m² for Level 4 (tape + 2 coats) = 20.2 L (USG: about 0.38–0.41 L per m² for a three-coat job). |
| 1 roll | Paper joint tape76.2 m roll | 60.11 m: about 1.2 m per m² of board (USG), seams and inside corners. |
| 2 × 3.78 L | Drywall primer (PVA)1 coat | 49.5 m² ÷ 27.9 m² per 3.78 L = 6.7 L. Seals the paper and the compound so the paint dries evenly. |
| 1 pack | Drywall sanding screens120–150 grit, 10-pack | About one pack per 55.7 m² of board: a light pass after each coat dries, never through to the paper. |