Sheet S-39 · Build a paver patio
16′ × 12′ paver patio
- Pavers
- 208sq ft · ≈936 pieces
- Base
- 5cu yd · 6″ compacted
- Sand
- 34bags bedding
- Edging
- 40ft · 6 sections
Tools you need
- Mason's line + stakes
- Line level
- Tape measure (25 ft)
- 4-ft level
- Square shovel
- Round-point shovel
21 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 5 cu yd delivered | Crushed stone base, bulk¾″ minus crushed stone, with fines | 17′ × 12′ 6″ (the patio + 6″ past the three open sides) = 213 sq ft × 6″ deep, +20% because it compacts = 127.5 cu ft — about 7 tons. Order it delivered (255 bags otherwise). No stone dust: it holds water. |
| 34 bags | Leveling sand1″ bedding, coarse | 192 sq ft × 1″ + 5% for screeding = 16.8 cu ft ÷ 0.5 cu ft a bag. Coarse sand, not fine play sand. |
| 208 sq ft (≈936 pieces) | Concrete pavers4×8 (Holland), 2⅜″ (60 mm) thick | 192 sq ft + 5% for a running bond pattern + 3% for the edge cuts; 4.5 pieces a sq ft with joints. Buy from one lot number so the color matches; check the pallet’s coverage. |
| 6 sections | Paver edge restraint, 6′8″ sections6′ 8″ sections | 40 ft of open edge (none along the house) ÷ 6′ 8″ a section. |
| 5 bags | Polymeric joint sand, 50 lb50 lb bags | 192 sq ft + 10% for topping up ÷ about 50 sq ft a bag for 4×8 brick-style pavers with narrow joints. Wider joints and thicker pavers take more: read the bag’s chart. |
| 2 pieces | EMT conduit 1-inch × 10 ft1-inch × 10′ | Two pipes on the base set the sand at 1″; a straight 2×4 screeds between them. |
| 1 board | 2×42×4 × 10′ | Pick the straightest one: it drags the sand flat across the pipes. |
| 9 stakes | Wood stakes18″ | Corners and every 8 ft or so, for the string lines that set the edges and the slope. |
Sheet S-39 · Build a paver patio
4.88 m × 3.66 m paver patio
- Pavers
- 19.3m² · ≈936 pieces
- Base
- 4m³ · 152 mm compacted
- Sand
- 34bags bedding
- Edging
- 12.2m · 6 sections
Tools you need
- Mason's line + stakes
- Line level
- Tape measure (7.5 m)
- 1.2 m level
- Square shovel
- Round-point shovel
21 tools on the Sheet, each marked own, buy or rent
| Buy | Item | How we got this |
|---|---|---|
| 4 m³ delivered | Crushed stone base, bulk19 mm minus crushed stone, with fines | 5.18 m × 3.81 m (the patio + 152 mm past the three open sides) = 19.7 m² × 152 mm deep, +20% because it compacts = 3.61 m³ — about 6.4 tonnes. Order it delivered (255 bags otherwise). No stone dust: it holds water. |
| 34 bags | Leveling sand25 mm bedding, coarse | 17.8 m² × 25 mm + 5% for screeding = 0.48 m³ ÷ 0.014 m³ a bag. Coarse sand, not fine play sand. |
| 19.3 m² (≈936 pieces) | Concrete pavers4×8 (Holland), 60 mm thick | 17.8 m² + 5% for a running bond pattern + 3% for the edge cuts; 48.4 pieces a m² with joints. Buy from one lot number so the color matches; check the pallet’s coverage. |
| 6 sections | Paver edge restraint, 2.03 m sections | 12.19 m of open edge (none along the house) ÷ 2.03 m a section. |
| 5 bags | Polymeric joint sand, 22.7 kg22.7 kg bags | 17.8 m² + 10% for topping up ÷ about 4.6 m² a bag for 4×8 brick-style pavers with narrow joints. Wider joints and thicker pavers take more: read the bag’s chart. |
| 2 pieces | EMT conduit 1-inch × 3.05 m | Two pipes on the base set the sand at 25 mm; a straight 2×4 screeds between them. |
| 1 board | 2×42×4 × 3.05 m | Pick the straightest one: it drags the sand flat across the pipes. |
| 9 stakes | Wood stakes457 mm | Corners and every 2.44 m or so, for the string lines that set the edges and the slope. |